Ga naar hoofdinhoud
20230710 151515

Start of steel construction

Jul 10, 2023

After officially driving the first pile into ground on May 4 for the new factory halls on Maasvlakte 2, we reached another milestone on July 10: the first truss of the steel structure for hall C was placed.

Once the expanded manufacturing plant is fully ramped-up, which is expected in the first half of 2025, the upgraded manufacturing plant will significantly increase the total combined capacity of Sif to 500 kilotons a year and upgrade Sif’s capabilities to manufacture the equivalent of 200 XXXL, 11 meter diameter, 2,500 tons reference monopile foundations a year.

20230710 151515